Malacca PlanetariumCADANGAN MEREKABENTUK, MEMBINA DAN MENYIAPKAN ' PLANETARIUM' SECARA ' DESIGN AND BUILD' DI KAWASAN BULATAN MITC (LOT 5484), MUKIM BUKIT BARU, DAEARAH MELAKA TENGAH. MELAKA.
'- Planetarium System Installation Works
Owner: Kerajaan Negeri Melaka
Project Management Consultant : Perbadanan Kemajuan Negeri Melaka
Architect: LCH Architect
Contract Value: RM 4,825,000.00
Completion: Dec 2008
____________________________________________________________________
MAS DOCKING CONTROL SYSTEM
DESIGN, FABRICATION, DELIVERY TO SITE, INSTALLATION, TESTING AND COMMISSIONING OF B777-200 & A330-200/300 DOCKING SYSTEM & B737 - ALL SERIES (except 100) & B737 - ALL SERIES (except 100)& A320 DOKCKING SYSTEM.'- Structure and Control Electrical Installation Works
Owner: MALAYSIAN AIRLINES SYSTEM BERHAD
Main Contractor: STAM STRARCH SDN BHD
Consultant: ENMAC SEKUTU SDN BHD
Automation Specialist: PROTECH BUILDERS
Contract Value: RM 1,590,000.00
Completion: August 2008
____________________________________________________________________
Mydin Shopping Center
CADANGAN PEMBANGUNAN YANG TERDIRI DARIPADA :PASARAYA BORONG 2 1/2 TINGKAT YANG MENGANDUNGI :
- PASARAYA BORONG, MEDAN SELERA, GEDUNG MEMBELI BELAH, PENCAWANG ELEKTRIK, KEBUK SAMPAH, GUDANG, TEMPAT MEMUNGGAH BARANG, TEMPAT LETAK KERETA DAN SEBUAH PONDOK PERHENTIAN BAS DAN SEBUAH PONDOK PENGAWAL DI TINGKAT BAWAH.
- PASARAYA BORONG, PEJABAT, GUDANG, ASRAMA DAN PUSAT LATIHAN DI TINGKAT SATU SERTA KEMUDAHAN BERKAITAN.
- ASRAMA DI TINGKAT SATU MEZANIN SERTA KEMUDAHAN BERKAITAN DI ATAS LOT-LOT 15060, 15061 & 15062 MUKIM KATIL, DAERAH MELAKA TENGAH, MELAKA BANDARAYA BERSEJARAH.
'- Electrical Installation Works
Owner: Welson Wholesale Cash & Carry (M) Sdn. Bhd
Main Contractor: Pembinaan TujuSetia Sdn. Bhd
M & E Consultant: Norman Disney & Young Sdn. Bhd
Contract Value: RM 8,100,000.00
Completion: Dec 2008
____________________________________________________________________Owner: Welson Wholesale Cash & Carry (M) Sdn. Bhd
Main Contractor: Pembinaan TujuSetia Sdn. Bhd
M & E Consultant: Norman Disney & Young Sdn. Bhd
Contract Value: RM 8,100,000.00
Completion: Dec 2008
SANDAKAN WATER SUPPLY SCHEME
'- Electrical Installation Works
Owner: Kerajaan Negeri Sabah, Jabatan Air Sabah
Turnkey Contractor: City Best Corporation Sdn. Bhd
M & E Contractor: Water Engineering Technology Sdn. Bhd.
Jurutera Perunding: Jurutera Perunding Kinakota Sdn. Bhd.
Contract Value: RM 2,960,000.00
Completion: June 2008